Analysis of Activity Planning In the 2765 Dwt Tanker Repair Process Using the Critical Path Method (Cpm)
shipyard ; critical path method (cpm) ; project scheduling.
DOI:
https://doi.org/10.30587/ivrj.v2i1.5080Keywords:
shipyard ; critical path method (cpm) ; project scheduling.Abstract
Ships are basically a means of sea transportation, which connects an island or between regions of a country, which is used as passenger transportation, as well as transportation of goods. As the largest archipelagic country in the world, Indonesia has waters with two vast seas which are larger than the land. Therefore, sea transportation has an important role for the sustainability of the economy in Indonesia, so the need for developers in the maritime sector needs to be increased, one of which is in the field of Shipyards. In the ongoing docking process, it is necessary to schedule the work. So that the project runs in a structured manner, it is necessary to pay attention, because scheduling a project itself helps to detail the activities of an activity, the time required for project completion so that the project is on time Completion and there are no delays in workmanship Critical path method (CPM) itself is a method for identifying completion in a project to complete the completion of a project so that it is on time. And the authors use this method to help resolve and compare between the 2765 dwt tanker scheduling made by the shipyard and using the critical path method (CPM). The results of my research entitled " analysis of activity planning in the 2765 dwt tanker repair process using the critical path method (cpm) " are. The schedule made by the shipyard gets a completion time of 61 days, whereas if you use the critical path method, it takes 48 days.
References
Faizti, N. (2021). Getting to Know the Kinds of Qualitative Data Analysis in Research.
Hadi. (2016). Data validity check. CHECKING THE AUTHORITY OF QUALITATIVE RESEARCH DATA ON THESIS , 75.
Olivia, D., Afma, VM, & Anna, B. (2014). Improvement Scheduling Design for the 42 M Tug Boat Building Project with the Critical Path Method at PT. Batam Expressindo Shipyard. University of Riau Archipelago Batam.
Pradistya, RM (2021, February 10). Triangulation Techniques in Qualitative Data Processing . Retrieved August 4, 2021, from DQLab: https://www.dqlab.id/teknik-triangulation-dalam-pengolahan-data-kualitatif
Prasetyoko, RT (2011). Project Scheduling Evaluation Using the CPM (Critical Path Method) and "S" Curve Analysis on the Cold Storage (Condencing Unit) Manufacturing Project at CV. Sidoarjo Engineering Development. Faculty of Industrial Technology of the National Development University "Veteran".
Tardok, EL (2018). Time Acceleration Analysis Using the CPM and Pert Methods in the Tanjung Priok Port Pier Development Project. Faculty of Marine Technology Sepuluh Nopember Institute of Technology Surabaya.
A. Shah Ali, A. Smith, M. Pitt, and C. Hong Choon, “CONTRACTORS' PERCEPTION OF FACTORS CONTRIBUTING TO PROJECT DELAY: CASE STUDIES OF C OMMERCIAL PROJECTS IN KLANG VALLEY, MALAYSIA.”
J. Results, K. Scientific, G. Regatama, W. Amiruddin, and P. Mulyatno, "JOURNAL OF SHIPPING ENGINEERING Network Planning Analysis of SPB TITAN 70 Ship Repair Using the Critical Path Method," J. Tek. Shipping , vol. 7, no. 4, 2019, [Online]. Available: https://ejournal3.undip.ac.id/index.php/naval
YT Andhani, IP Mulyatno, and AWB Santosa, “KN Ship Repair Reschedule. KUMBA 470 DWT with the Critical Path Method in the Semarang Shipyard,” J. Tek. Shipping , vol. 8, no. 3, pp. 231–238, 2020.
Shipbuilding Vocational High School Curriculum Team, Faculty of Marine Technology ITS, "Types of Docks and Their Functions," pp. 1–41, 2003.
BKI, “Rules for Classification and Surveys,” vol. I, no. January, 2014.
AM & SP Day T Handoko, Fundamentals of Operations Research . Yogyakarta: BPFE., 1993.
Siswanto, Operations Research vol 1 . Jakarta: Erlangga., 2007.
Chirillo, LD, RD Chirillo and Y. Okayama., 1983, Integrated Hull Outfitting and Painting , NSRP, Maritime Administration in cooperation with Todd Facific Shipyard Corp, USA.
Carmichael AW, 1919, Practical Ship Production First Edition , McGraw-Hill Book Company Inc, New York.
House and Hill, 2000” Guide to Ship Repair Estimates”. Elsevier Butterworth – Heinemann.
PAL Indonesia, 2000, Refresher Training: New Shipbuilding Management System; Production Planning For Managers , PT.PAL Indonesia, Surabaya.
Storch, RL, Ham Minggu, CP, and Bunch, HM., 1995, Ship Production Second Revision , Cornell Maritime Press, Centreville.
Shipping Vocational High School Curriculum Team, 2003, Get to Know the Types of Ships, Ministry of National Education.
Watson DGM, 2002, Practical Ship Design . Elseiveir Science Ltd, London.
Jahidin, Saddam. Overview of Ship Production Process (ship production part 1). Learn Ship Blog. September 22, 2011. September 15, 2014.
Farisa Mukti Arta Mevia., Shipyard – Definition, Types, Methods and Industry https://wira.co.id/galangan-kapal/
Tardok, EL (2018). Time Acceleration Analysis Using the CPM and Pert Methods in the Tanjung Priok Port Pier Development Project. Faculty of Marine Technology Sepuluh Nopember Institute of Technology Surabaya.